Project Reviewed and Verified

This project record has been reviewed and approved by QA & M&E for public publication.

Agriculture, Irrigation, Livestock, Fisheries & Cooperative Development · 2023-2024

Supply of incubators in Makutano

Completed Project Reviewed and Verified KDSP II Project

When

Project timeline

Completed
Delayed by 723 days
Planned duration 365 days
Time elapsed 1088 days
Overdue 723 days
Physical progress 100%
Jul 1, 2023 Jun 30, 2024
  1. Approval
  2. Project start
  3. Expected completion
  4. Actual completion Not recorded

Overview

Project details

Programme / Project Category
KDSP II Project
Flagship project
No
Project code
Not provided
Programme (CIDP/ADP)
Not provided
Description
Supply of incubators to improve poultry production

Where

Location & Geography

Sub-County
Cherang'any
Ward
Makutano
Specific location
Makutano Ward
Additional wards
Not provided

When

Delivery status

Status
Completed
Physical progress
100%

Budget

Financial Details

Funding partners
County Government of Trans-Nzoia · KES 2,400,000 · 100.0%
Budget allocation
KES 2,400,000
Expenditure / disbursed
KES 2,323,860
Pending bills
KES 0
Funding source
County Government of Trans Nzoia
Financial year
2023-2024

Delivery

Implementation

Contractor
Not provided
Google Maps link
View on Google Maps
Challenges
Not provided

KDSP II Project

KDSP II Project — Programme-specific fields

Activity Number
Not provided
Sub-Activity
Not provided
Output Indicator
Incubators supplied
Target Value
Not provided
Baseline Value
Not provided
Achievement to Date
Not provided
Mitigation Measures
Not provided
Remarks/Comments
County Agriculture Stock-Take
Means of Verification
KDSP-II Verification
Number of Beneficiaries
Not provided

Progress

Progress updates

No progress updates recorded yet.

Citizen voice

Public feedback

No public feedback submitted yet. Be the first to share your views.